O'Connell Center + Florida Gymnasium — the first venue UF will run on Wi-Fi 7.
DriverGame-day concurrency on 2017 Wi-Fi 5 hardware. 9 × 2960-X feed every floor — PoE+ 30W ceiling forces the refresh.
A Wi-Fi 7 migration roadmap for the University of Florida — inventory-anchored, decision-oriented, FY2027 → FY2028.
01/03
Composition · Code Train · Controller Capacity
CW9800H2 native + single code train. The capex question lives at the access layer — not the head.
The platform can support the Wi-Fi 7 pilot without a controller purchase.
UF can move from Wi-Fi 6 lifecycle to Wi-Fi 7 readiness without protecting a stranded 6E investment.
APs, switches, cabling, power, and policy enforcement are the true FY27 workstream.
IOS-XE 17.15.5.36 — single image, single change window.
CW9800H2 — capex conversation does not start at the controller.
~48K capacity vs 10K deployed. Zero rip-and-replace.
Direct. 0 Wi-Fi 6E APs — the gap is the lever.
02/03
A 32,000-seat venue · 9 access switches · one ceiling
0%
of the floor still running Wi-Fi 5.
A 32,000-seat venue. Mixed workloads — guest streaming, point-of-sale, IoT, broadcast. One ceiling.
Ten APs on Wi-Fi 6 — and they belong to Ticketmaster. Tenant-owned, deferred to Wave 2.
Source · UF NetOps · cisco.com c51-744432 · audit 6e2f-a91
Catalyst 2960-X — all access
Need full refreshPoE+ ceiling · Wi-Fi 7 client AP needs more
Wi-Fi 7 baseline · 60 W · 802.3btSingle-gig — Wi-Fi 7 PHY is 18 Gbps
Wi-Fi 7 baseline · 10 G · mGigFive topics, one decision. The chassis under the floor is the chassis that decides what Wi-Fi 7 can actually do here. UFIT × Cisco read-in · 2026-05-23
03/03
Arena · Campus · Facilities — three stages, one trajectory
O'Connell Center + Florida Gymnasium — the first venue UF will run on Wi-Fi 7.
DriverGame-day concurrency on 2017 Wi-Fi 5 hardware. 9 × 2960-X feed every floor — PoE+ 30W ceiling forces the refresh.
Academic main campus — high-density classrooms + research labs come online behind the Arena.
Driver2960-X LDoS October 2027 · AIR-AP3802 LDoS April 2027. The forcing function lives inside the same fiscal year.
Dorms · Ben Hill Griffin Stadium · extension offices — lifecycle-driven, not urgency-driven.
DriverNormal AP lifecycle cadence. No emergency-EOS pressure — Stage 01 + 02 absorbed the FY27 forcing functions.
390 units in unsupported territory. No bug fixes, no CVE remediation. Flag to UFIT security as near-term risk — but the TMP trade-in pool absorbs the refresh cost.
Cat6A required for 10G mGig at full reach. O'Connell vintage likely Cat5e / Cat6. Audit before Phase 3.
Wi-Fi 7 at 60W/AP = 4–5× per-port draw. UPS / PDU resizing in some IDFs.
Older Bowl AP runs may not terminate at new switch-closet locations. Site survey confirms.
2,563-AP coverage gap — Housing IT separate Catalyst Center domain. Reconcile before Wave 2.
Confirm SGT enforcement parity across wired + wireless + physical security. Required for cyber-physical convergence.
BOM lock 31–90 days prior. Pre-basketball cutover window. UF + Cisco joint Readiness Assessment unlocks Phase 1.